Boehringer Ingelheim Austria

Boehringer Ingelheim Austria
MCE Anlagenbau Austria

Vienna, Austria

2003-2005

Biopharmaceutical medication production

Boehringer Ingelheim, Wien. Photo ©  Robert Tober, www.toro.cc

Scope of services

- Execution planning of the balanced sprinkler system in 3D
- Planning and tender offer for the supply of fire water and the supply ring for the entire site
- Preparation of material extracts
- Construction supervision

Characteristics of the project

- Balanced, doubly locked sprinkler system
- approx. 16,500 m³ protected area
- 23 extinguishing areas
HOYER Brandschutz (formerly Sprinklerplan) was commissioned to plan the sprinkler system according to FM- and TRVB-guidelines. That is why special attention had to be paid to the exclusion of faulty alarms and the very expensive process and ventilation installation. An additional planning job comprised a new central pump with two fire water supply basins as well as a ring pipe system to be able to supply all buildings on the site with fire water from two directions.
For the allocation of the construction, service specifications were prepared. The evaluation of the offers and quotations as well as technical customer support in the awarding of contracts complete the spectrum of services.